Case Study

Incusa - Saint Gobain

Carrascal del Río, Spain

Potential impact on water or groundwater

The site is in an ecological area with a high level of protection.

The water is discharged into a mountain river with salmon fisheries.

The water consumption for cleaning is 1500 m3/h with two circuits: neutral an acid (feldspar production).

Aggregates are by-products.

Action on

Treatment plant/Mining waste treatment.

Description of the good practice

95% of water recovery and recirculation;

5% of loss due to wet content in products and to the fresh water needed in acid circuit.

In the beginning, acid water was neutralized in a sedimentation pond by precipitation of pollutant elements with excess of calcium hydroxide in a 12 hours reaction process. A new plant designed for a continuous pH monitoring and control, with addition of calcium hydroxide according to the pH of water and continuous extraction of the precipitate (solid) fraction in a 14 hours. A press filter reduces humidity to less than 5%.

Description of the positive effects on water/groundwater

A better control of pH.

Disposal of the solid fraction with less water content.

Elimination of the risk of acid water drainage.

Status

In 2018, the project was still on going.

Environment Water Management Case Study